In April 2020, our team was tasked with backfilling three underground sewage detention tanks for a project in Singleton In NSW.
Stone slingers / rock slingers are ideal for backfilling underground sewage detention tanks.
The one-day project involved backfilling three underground tanks. The site presented challenges for traditional methods as only one corner of the excavation provided access.
The small footprint of our stone slinger / rock slinger meant material could be stockpiled onsite enabling deliveries of material to continue throughout the backfill process.
We placed 700 tonnes of 10-14mm gravel in just under 8 hours.